Masonry: Vertical Rebar Bars And Footage For A Wall

Excel Formulas › Masonry

All versions

Reinforced block walls get vertical bars at a fixed spacing, and the count always runs one more than the number of gaps. This recipe converts the wall length to inches, divides by the spacing, rounds up and adds the end bar, then multiplies by the wall height to get total bar footage to order.


Quick formula: Wall length in inches over spacing, rounded up, plus the end bar:
=ROUNDUP(B2*12/C2,0)+1

A 24-foot wall with bars every 32 inches needs 10 bars, or 80 feet at 8 feet high.

Functions used (tap for the full reference guide):

The example

Three walls at different lengths and spacings. Tighter spacing means more bars.

ABCDEF
1CaseWall ftSpacing inHeight ftBarsTotal ft
2Garden wall243281080
3Retaining wall30488972
4Warehouse wall40241021210

The formula

Gaps between bars, rounded up, plus one for the closing bar:

=ROUNDUP(B2*12/C2,0)+1 // bars needed; total feet = bars * height

How it works

Here is the logic, one piece at a time:

  1. B2*12 converts the wall length from feet to inches.
  2. Dividing by the spacing in C2 counts the gaps between bars.
  3. ROUNDUP(...,0) rounds partial gaps up so the last section is still reinforced.
  4. +1 adds the extra bar at the end because bars equal gaps plus one.

Local code or the engineer's drawings set the spacing; this formula only counts the bars.

Try it: interactive demo

Interactive

Enter the wall length, bar spacing and wall height.

Variations

Add a bar at each corner and opening

Add extra bars for corners and either side of openings.

=ROUNDUP(B2*12/C2,0)+1+CornerBars

Add lap length

Add a lap length per bar if bars are spliced.

=E2*(D2+LapFeet)

Pitfalls & errors

Forgetting the +1 leaves the last cell without a bar.

Spacing is measured center to center, and the first bar is usually placed at the wall end, not at a spacing offset.

Order bar in stock lengths and note laps so you do not buy short.

Practice workbook

📊
Download the free Masonry: Vertical Rebar Bars And Footage For A Wall practice workbook
Edit the yellow length, spacing and height cells; bars and footage recalculate.

Frequently asked questions

Does this include horizontal bond beam steel?
No. Count horizontal bars separately by courses and wall length.
Why round up rather than to nearest?
A partial gap still needs a bar at its end.

Stop fighting formulas. Learn them in a day.

This recipe is one of hundreds of real-world formulas we teach. Our Excel Formulas & Functions class covers lookups, logic, text, and dynamic arrays hands-on — live in Dallas–Fort Worth, Houston, Austin, Oklahoma City, Denver, or online.

See the Formulas & Functions Class

Related formulas: Masonry: Mortar Bags for a Block Wall · Masonry: Block Courses in a Wall · Fencing: Concrete Bags Needed For Post Holes

Function references: ROUNDUP