Labor Hours and Cost from a Crew

Excel Formulas › Construction & Trades

All versions

Estimate a task’s labor from a production rate — how much one worker completes per hour. Divide the quantity by the crew’s combined rate for hours, then multiply by the wage for cost.


Quick formula: crew-hours to complete a quantity:
=quantity / (crew_size * units_per_worker_hour)
Quantity divided by the crew's total hourly output gives the hours; times wage and crew size gives cost.

The example

2,000 sq ft, 3-worker crew, 50 sf/hr each.

AB
1ItemValue
2Crew output/hr150
32000 ÷ 150→ 13.3 hrs

The formula

The formula:

=B2 / (crew_size * rate) // qty ÷ crew output

How it works

How it works:

  1. A production rate is units one worker finishes per hour (e.g. 50 sq ft of drywall).
  2. Crew output = crew size × rate — the team’s combined hourly pace.
  3. Divide the quantity by crew output for the elapsed hours on the job.
  4. Total labor cost = elapsed hours × crew size × hourly wage (or sum individual wages).

Crew-hours vs elapsed hours. Elapsed hours is how long the job takes; crew-hours (or man-hours) is elapsed × crew size — the figure you cost and bill. A 13.3-hour job with a 3-person crew is 40 crew-hours of labor. Keep the two straight or your labor cost will be off by the crew size.

Try it: interactive demo

Live demo

Quantity, crew size, rate per worker-hour, wage.

Hours · Cost

Variations

Crew-hours (man-hours)

Billed labor:

=elapsed_hours * crew_size

Labor cost

Crew-hours × wage:

=crew_hours * hourly_wage

Days on site

From an 8-hr day:

=ROUNDUP(elapsed_hours / 8, 0)

Pitfalls & errors

Elapsed vs crew-hours. Cost labor by crew-hours (elapsed × crew), not elapsed alone.

Realistic rates. Use production rates that include setup and breaks, not peak pace.

Round days up. A partial day still books a full crew.

Practice workbook

📊
Download the free Labor Hours and Cost from a Crew practice workbook
A crew-labor sheet with the crew-hours, labor-cost, and days variants, plus 4 challenges with answers. No sign-up required.

Frequently asked questions

How do I estimate labor hours from a crew in Excel?
Divide the quantity by crew output: =quantity / (crew_size * units_per_worker_hour) gives elapsed hours.
What's the difference between elapsed and crew-hours?
Elapsed is how long it takes; crew-hours (man-hours) is elapsed × crew size — the figure you cost and bill.
How do I get labor cost?
Multiply crew-hours by the hourly wage: =crew_hours * hourly_wage.

Stop fighting formulas. Learn them in a day.

This recipe is one of hundreds of real-world formulas we teach. Our Excel Formulas & Functions class covers lookups, logic, text, and dynamic arrays hands-on — live in Dallas–Fort Worth, Houston, Austin, Oklahoma City, Denver, or online.

See the Formulas & Functions Class

Related formulas: Labor hours · Cost per square foot · Tiered overtime pay