Concrete Volume in Cubic Yards

Excel Formulas › Construction & Trades

All versionsROUNDUP

Concrete is sold by the cubic yard, but you measure in feet. Compute volume in cubic feet (length × width × thickness), divide by 27, and round up to order the right amount.


Quick formula: cubic yards for a slab:
=ROUNDUP(length_ft * width_ft * (thickness_in / 12) / 27, 2)
Volume in cubic feet (thickness converted to feet) divided by 27 cubic feet per yard.

Functions used (tap for the full reference guide):

The example

20 × 10 ft slab, 4 in thick.

AB
1ItemValue
2Area (ft²)200
34 in → yd³→ 2.47

The formula

The formula:

=ROUNDUP(L * W * (T_in / 12) / 27, 2) // cu ft ÷ 27

How it works

How it works:

  1. Convert thickness to feet: inches ÷ 12 (a 4-inch slab is 0.333 ft).
  2. Multiply length × width × thickness for cubic feet.
  3. Divide by 27 — there are 27 cubic feet in a cubic yard.
  4. Round up and add a small waste allowance (5–10%) for spillage and uneven subgrade.

Add a safety margin. Running short mid-pour means a cold joint or an emergency second truck. Most estimators order =ROUNDUP(yards * 1.10, 2) — a 10% cushion — or round up to the nearest quarter-yard the supplier delivers. Over-ordering a little is far cheaper than coming up short.

Try it: interactive demo

Live demo

Length, width (ft) and thickness (in).

Cubic yards:

Variations

With 10% waste

Safety margin:

=ROUNDUP(yards * 1.10, 2)

Bags for small jobs

From cu ft:

=ROUNDUP(cubic_feet / bag_yield, 0)

Cost of pour

Yards × price:

=yards * price_per_yard

Pitfalls & errors

Convert thickness. Inches must become feet (÷12) before multiplying.

27, not 9. A cubic yard is 27 cubic feet (3³), not 9.

Order a cushion. Round up and add waste — running short mid-pour is costly.

Practice workbook

📊
Download the free Concrete Volume in Cubic Yards practice workbook
A concrete sheet with the waste, bags, and cost variants, plus 4 challenges with answers. No sign-up required.

Frequently asked questions

How do I calculate cubic yards of concrete in Excel?
Use =ROUNDUP(length * width * (thickness_in/12) / 27, 2). Convert thickness to feet and divide cubic feet by 27.
How many cubic feet are in a cubic yard?
27 — a cubic yard is 3×3×3 feet.
Should I add waste to a concrete order?
Yes — add about 10% (=ROUNDUP(yards*1.10, 2)) or round up to the supplier's delivery increment to avoid running short.

Stop fighting formulas. Learn them in a day.

This recipe is one of hundreds of real-world formulas we teach. Our Excel Formulas & Functions class covers lookups, logic, text, and dynamic arrays hands-on — live in Dallas–Fort Worth, Houston, Austin, Oklahoma City, Denver, or online.

See the Formulas & Functions Class

Related formulas: Concrete volume · Square footage area · Material with waste

Function references: ROUNDUP